| Project Name: Handicap
Improvements and Door Modifications Stoughton High School, Stoughton,
MA
Owner: Town of Stoughton,
MA
Contract Amount: $1,749,279
Completion Date: December 2004
|
| Project
Scope: The project consisted of making the Stoughton High School
handicap accessible, which included replacement of all doors and
hardware within the building, complete bathroom and lavatory renovations,
and fire alarm upgrades. The project was performed while the building
was occupied and continued thru to a second shift to expedite completion.
|