Home   |    Services   |    Portfolio   |    Recognition   |    Company Profile   |    Personnel Bios   |    Contact Us

Maron   C o n s t r u c t i o n   Co m p a n y ' s   P o r t f o l i o







Historical Renovation

Housing

Design Build

Athletics

Utilities

Educational

Defense

Special Projects


Historical Renovation

Project Name: Looff Carousel

Owner: City of East Providence
Contract Amount: $715,735
Completion Date: May 2004

Project Scope: The project consisted of the construction of a complete new structural concrete foundation walls for the building foundation and for the undercarriage of the carousel. The existing space limitation, of as little as two feet, made this project especially challenging. In addition to the foundation work, we also restored all the existing windows, provided new roofing and a new cupola.


Project Name: Renovation to Peacedale Library

Owner: Town of South Kingstown
Contract Amount: $350,000
Completion Date: November 1996

Project Scope: This project consisted of the replacement of the exterior trim and roofing at the historic Hazard library. It involved matched all profiles of wood trim and the provision of an historical replicated roof shingle.


Project Name: Stadium Theatre Renovation Phase 2, 4 and 5



Owner: Stadium Theatre Foundation- Woonsocket
Contract Amount: $1,560,000
Completion Date: June 2004



Project Scope: Maron Construction performed three phases of renovations to the Stadium Theatre. The first and second phases consisted of a complete new HVAC system, new roof and complete new Electrical Distribution system. In addition, all new stage lighting, controls and curtains were installed. The third phase consisted of the reconstruction of the lobby area of this turn of the century theatre.


Project Name: Window Restoration- RI State House

Owner: State of Rhode Island
Contract Amount: $1,261,000
Completion Date: June 2000

Project Scope: This project consisted of the replication of the original doors and windows at the Rhode Island State House. The windows were of the same species and style as the original, as was the new hardware. We had to replicate the exact paint color of the original windows.


Housing

Project Name: Barrack Renovations- US Coast Guard- Martha’s Vineyard

Owner: United States Coast Guard
Contract Amount: $1,041,118
Completion Date: February 2005

Project Scope: The project consisted of the removal of the partial second floor and roof and the addition of a full size second floor. Also included was the complete renovation of the first floor space. All new mechanical, plumbing, electrical and architectural finishes were utilized throughout the facility. This project was challenging because of the location. Material and manpower had to be imported to the island.


Project Name: Renovations to Morin Heights Housing

Owner: Woonsocket Housing Authority
Contract Amount: $8,854,487
Completion Date: September 2006

Project Scope: This project consisted of renovations and additions to 9 buildings for the Woonsocket Housing Authority. It included extensive renovations to the interiors, including new kitchens, heating and plumbing systems. The exterior of the buildings had new roof and siding installed. Extensive sitework between building were performed. This project was performed in three phases in order to facilitate movement of tenants from one building to another.


Project Name: Little Four Renovations- URI

Owner: State of Rhode Island
Contract Amount: $9,091,572
Completion Date: August 2007

Project Scope: This project consisted of the renovation to four college dormitories located on the main campus of the University of Rhode Island. They include asbestos abatement, aluminum windows, new wall and floor finishes, life safety system including a new fire alarm and wet sprinkler system. Also included were the construction of small additions to house a new elevator for handicap accessibility. This project was phased over two years.


Project Name: Renovation to Heathman Hall- URI

Owner: State of Rhode Island
Contract Amount: $6,314,151
Completion Date: September 2006

Project Scope: This project consisted of the complete renovation of the Heathman Hall Dormitory located on the main campus of the University of Rhode Island. It included new Mechanical, Plumbing, and Electrical systems. It also included renovations to the bathrooms, student rooms and common areas. Life safety systems were installed throughout the building. Extensive site renovations were required to make the building ADA compliant. This project was phased over two summers, while the students were not in school.


Design / Build

Project Name: Cafeteria Renovations- Hewitt Hall

Owner: Department of Navy, Newport, RI
Contract Amount: $625,000
Completion Date: December 2000

Project Scope: This project was performed on a design build basis with the Department of Navy where we converted an open space into a complete industrial kitchen, a cafeteria serving area, a luncheon sit down area and a VIP dining room. This project consisted of many high quality products and was a showcase at the Naval War College. This project received many accommodations for its quick turnover and the quality of workmanship.


Project Name: Saylesville Elementary & Lonsdale Avenue Schools

Owner: Town of Lincoln, RI
Contract Amount: $309,150
Completion Date: August 2001

Project Scope: Project Scope: This was a design build project which consisted of a small addition to an elementary school, which had all facets of construction from Division 2-16. The other portion was a classroom fit-out whereby the Town split up larger classrooms into smaller ones. Again, most facets of construction were utilized.


Project Name: Renovations to Building 172

Owner: Department of the Navy
Contract Amount: $2,372,000
Completion Date: December 1995

Project Scope: This Design build project consisted of the complete exterior façade of the building for energy code issues. It included a complete insulation and dryvit system, with associated windows and appurtenances.


Athletics

Project Name: Renovations to Roland Hall

Owner: U.S. Coast Guard Academy, New London, CT
Contract Amount: $4,230,000
Completion Date: December 1997

Project Scope: This was a complicated rehabilitation project incorporating many phases of work in an occupied building. Various interior aspects of the building were demolished and rebuilt in its entirety. In addition, a complete new electrical, mechanical, and sprinkler system was installed throughout the five-story building. A complete new shower and gang toilet facility was built within the existing space. Finally, a very complicated mechanical room addition was installed to facilitate the installation of the new HVAC equipment. Throughout all this, the building remained occupied and in full use for the duration of the project.


Project Name: Auditorium Repairs & Gymnasium Improvements, Needham High School

Owner: Town of Needham
Contract Amount: $2,879,526
Completion Date: December 2000

Project Scope: Complete renovation to existing auditorium to include new seating, complete HVAC system, electrical, and all architectural finishes. Also, the refurbishment of the gymnasium to included new HVAC system, electrical system, bleachers, floor finishes, and architectural finishes. This project was performed while students were in the school.


Utilities

Project Name: Turbine Generator No. 6

Owner: Groton Subbase, Groton, CT
Contract Amount: $6,134,000
Completion Date: December 1996

Project Scope: The project consisted of installing a cogeneration plant at the boiler plant (Building 29). The project was high tech in nature which involved providing and installing a 5 mega watt turbine generator, a 50,000 lbs waste heat recovery boiler and a gas boost compressor. In addition to the above, two (2) small additions were installed, one of which was a 20’ high poured in place concrete shell and the other was a small metal building. The foundations consisted of wood sheet piling with massive concrete equipment foundations. Also included in the scope of work was a complete new electrical distribution system for the new facility.


Project Name: RISE Generator Service Building

Owner: Florida Power and Light
Contract Amount: $1,960,000
Completion Date: December 2001

Project Scope: The project consisted of the construction of a maintenance facility in support of the new Johnston, Rhode Island power plant. In addition, a follow up contract was provided for the fit-out of the generator building at the same location.


Project Name: Construct Base Utilities

Owner: National Guard, RI
Contract Amount: $2,246,719
Completion Date: June 2005

Project Scope: The project consisted of the replacement of the complete electrical and communication system for the entire National Guard base located in Quonset, Rhode Island. It involved keeping the existing systems in place while installation of the new systems were ongoing.


Educational

Project Name: John Eliot Elementary School, Needham, MA

Owner: Town of Needham
Contract Amount: $11,253,559
Completion Date: December 2003

Project Scope: The construction of a 45,000 sq ft elementary school for the Town of Needham. The work included demolition of the existing school, extensive site development, construction of a gymnasium, multi-purpose room, performance center, and baseball field. The construction was metal stud with brick back up and metal siding. All aspects of construction were utilized from Division 2-17, including specialized flooring systems.


Project Name: Sackett Street School Addition, Providence, RI

Owner: City of Providence
Contract Amount: $2,750,000
Completion Date: December 1998

Project Scope: Construction of an addition to the Sackett Street Elementary School for the City of Providence. Block construction was utilized for both the exterior shell and interior partitions. Structural steel and precast planking were utilized in certain sections of the addition. All aspects of construction were utilized from Division 2-16. In addition, a very aggressive schedule was required in order to open a portion of the addition for the start of the school year.


Project Name: Handicap Improvements and Door Modifications Stoughton High School, Stoughton, MA

Owner: Town of Stoughton, MA
Contract Amount: $1,749,279
Completion Date: December 2004

Project Scope: The project consisted of making the Stoughton High School handicap accessible, which included replacement of all doors and hardware within the building, complete bathroom and lavatory renovations, and fire alarm upgrades. The project was performed while the building was occupied and continued thru to a second shift to expedite completion.


Project Name: Façade Improvements, Nantucket Elementary School Nantucket, MA

Owner: Town of Nantucket
Contract Amount: $1,463,057
Completion Date: November 2004

Project Scope: The project consisted of complete siding, roofing and window replacement for the only elementary school on Nantucket Island. This project was unique and challenging because of its location and difficulty in accessing equipment and manpower to perform the work, both of which had to be provided from off-island sources. In addition, the work had to be performed over a very short time duration (summer break).


Project Title: Hope Dining Hall- URI

Owner: State of RI
Contract Amount: $18,208,442
Completion Date: May 2007

Project Scope: The project consisted of the construction of a new state of the Art dining facility located on the main campus of The University of Rhode Island. This unique project is the first certified “Green Building” performed by the State of Rhode Island. It received the LEEDS Silver Certification. Extensive sitework was required in order for accessibility to be achieved from the neighboring Little Four Dormitories.


Defense

Project Name: EM Sensor Testing Facility Building 68

Owner: Department of Navy, Newport, RI
Contract Amount: $2,979,000
Completion Date: November 1997

Project Scope: The project involved the complete interior demolition of a portion of Building 68 at Pier No. 2 and the complete rebuilding of all new mechanical, electrical, sprinkler, plumbing, and architectural finishes. In addition, a 60’ high tower addition was built to service the needs of the client. The building was being utilized by the NUWC personnel for torpedo testing. The Department of Navy was so pleased with our performance, a change order was provided to outfit another portion of the building.


Project Name: Undersea Battlespace Laboratory, Newport, RI

Owner: Department of Navy
Contract Amount: $7,420,636
Completion Date: June 2002

Project Scope: Construction of a four-story office/training facility for the Department of Navy to included demolition of existing structures, metal stud and brick back up, structural steel frame, interior drywall and block partitions, high tech electrical and mechanical systems, sprinkler systems, extensive millwork package and various architectural finishes. All aspects of construction were utilized from Division 2-17.


Special Projects

Project Name: Renovations to J. Joseph Garrahy Complex, Providence, RI

Owner: State of Rhode Island
Contract Amount: $3,172,910
Completion Date: January 2002

Project Scope: The project consisted of the complete renovation to a 6-story courthouse facility, including new courtroom finishes, lobby finishes, electrical system. The project had to be performed at night in order for the court system to operate uninterrupted.